UP-DATE ON DEVELOPMENT WORKS OF THE SOCIETY (UPDATED ON 05-04-2018)

 
Contractor: M/s Mian Abdul Jabbar & Co.
Expected revised project cost Rs. 295,051,303/-

Up to date payment (26th R.B)

Rs. 284,287,616 /-
Date of completion 31-12-2017
Financial Progress 96.35%
Physical progress 97.30%


Items
Description Total Estimated BOQ Quantity Previous Progress
Present
%age Progress
Roads
Embankment (Cft) 33,342 33,342
33,342
100%
Sewerage
Manhole (Nos) 750 750
742
96%
RCC Pipe (Rft) 57,100 51,435
57,982
100%
House Connection (Nos) 350 287
309
88.20%
RCC Pipe (House connection) Rft 13,000 10,864
11,575
89.00%
Water Supply System
Laying of W/S pipe line (Rft) 61,500 55,397
56,656
92.12%

Drainage System

 

Nullah Excavation (Rft) 4,500 Completed
Completed
100%
Box Culvert
Construction of Culvert (Nos) 2 Completed
Completed
100%
Under Ground Water Reservoir
Construction of Reservoir 2 100
Completed
100%
Parks Development
a) Boundary Wall (Nos) 2 Completed
Completed
100%
b) Grills & Gates (Nos) 2 Completed
Completed
100%
c) Paver Work (No.) 2 Completed
Completed
100%
Additional works (Road widening, Gate, Curb Stones, Guard Rooms etc)
- 100 98
98
98%

Construction of Small Plaza in Sector B

 
Contractor: M/s Saddique & Brothers

Up to date payment (9th IPC)

Rs. 17,112,099/-
Total project cost Rs. 17,549,545 /-
Financial Progress: 97.51%
Physical progress 99.00%
Date of completion 22-03-2017


Description
Status
%age Progress
Excavation
Completed
100%
P.C.C
Completed
100%
Raft Foundation
Completed
100%
Lower Ground Column & Slab Work
Completed
100%
Upper Ground Column & Slab Work
Completed 
100%
1st Floor Column & Slab Work
Completed 
100%

2nd Floor Column & Slab Work

Completed 
100%
Lower Ground & Upper Ground Brick work
Completed 
100%
1st & 2nd Floor Brick Work
Completed 
100%
Finishing works of lower ground
Almost completed 
99%
Finishing works of upper ground
Almost completed 
99%
Finishing works of 1st floor
In progress
98%
Finishing works of 2nd floor
In progress
98%

Construction of GABION Works (Lake Projects)

Contractor: M/s Sarfaraz Khan Khattak

Up to date payment (11th IPC)

Rs. 55,453,725/-
Expected project cost Rs. 67,038,377/-
Financial Progress: 82.71%
Physical progress 85.00%
Date of completion 31-01-2018


Description
Total Estimated BOQ Quantity
Previous Progress
Present Progress
%age Progress
Excavation works in normal soil
2,101,800 cft
965,782 cft
973,642
46.32%
Excavation works in hard rocks
244,000 cft
1,308,201 cft
1,559,986
100% executed Exceed from estimated quantity
Stone works in gabion
388,120  cft
551,471
551,471
100% executed, exceed from estimated quantity
PCC works in weir area
16,500
533
533
3.2%
RCC works in weir
8,500
-
-
-
GI wire mesh 382,993 399,649 449,649 100%
Stone pitching
30,000
9,000
29,949
99%

Construction of Main Gate in Sector D

Contractor: M/s Mian Abdul Jabbar & Co

Up to date payment (3rd IPC)

Rs. 3,540,217/-
Total project cost Rs. 4,384,145 /-
Financial Progress 80.75%
Physical progress 86.00%
Date of completion 13-08-2017


Description
Status
%age Progress
Excavation works in Foundation Completed 100%
Foundation work Completed 100%
RCC Column work Completed 100%
Brick work (Guard room) Completed 100%
Slab work (Guard room) Completed 100%
Main gate slab Completed 100%
Fixation of main gate Completed 100%
Finishing works In progress 90%

CONSTRUCTION OF MAIN GATE IN SECTOR D TOWARDS INTERCHANGE


GABION WORKS IN SECTOR D [LAKE PROJECT]



COMMERCIAL PLAZA IN SECTOR B [Completed and ready for possession]

Under construction Commercial Plaza in Sector B


Plantation in WAPDA Town Islamabad


Installation of Transformers in Sectors where houses have been constructed