UP-DATE ON DEVELOPMENT WORKS OF THE SOCIETY (UPDATED ON 15-10-2017)

 
Contractor: M/s Mian Abdul Jabbar & Co.
Up to date payment(24th R.B) Rs. 266,233,941/-
Expected project cost Rs. 295,051,303 /-
Present Financial Progress: 90.23%


Items
Description Total Estimated BOQ Quantity Previous Progress
Present
%age Progress
Roads
Embankment (Cft) 33,342 33,175
33,342
100%
Sewerage
Manhole (Nos) 750 689
720
96%
RCC Pipe (Rft) 57,100 48,530
51,435
90%
House Connection (Nos) 350 273
287
82%
RCC Pipe (House connection) Rft 13,000 10,430
10,864
83.57%
Water Supply System
Laying of W/S pipe line (Rft) 61,500 52,473
55,397
90.09%

Drainage System

 

Nullah Excavation (Rft) 4,500 Completed
Completed
100%
Box Culvert
Construction of Culvert (Nos) 2 Completed
Completed
100%
Under Ground Water Reservoir
Construction of Reservoir 2 100
100
100%
Parks Development
a) Boundary Wall (Nos) 2 Completed
Completed
100%
b) Grills & Gates (Nos) 2 Completed
Completed
100%
c) Paver Work (No.) 2 1.9
1.9
95%
Additional works (Road widening, Gate, Curb Stones, Guard Rooms etc)
- 100 98
98
98%

Construction of Small Plaza in Sector B

 
Contractor: M/s Saddique & Brothers

Up to date payment (8th IPC)

Rs. 15,248,702/-
Total project cost Rs. 17,549,545 /-
Present Financial Progress: 86.88%
Present physical progress 97.76%


Description
Status
%age Progress
Excavation
Completed
100%
P.C.C
Completed
100%
Raft Foundation
Completed
100%
Lower Ground Column & Slab Work
Completed
100%
Upper Ground Column & Slab Work
Completed 
100%
1st Floor Column & Slab Work
Completed 
100%

2nd Floor Column & Slab Work

Completed 
100%
Lower Ground & Upper Ground Brick work
Completed 
100%
1st & 2nd Floor Brick Work
Completed 
100%
Finishes works of lower ground
Almost completed 
99%
Finishes works of upper ground
Almost completed 
99%
Finishes works of 1st floor
In progress
88%
Finishes works of 2nd floor
In progress
85%

Construction of GABION Works (Lake Projects)

Contractor: M/s Sarfaraz Khan Khattak

Up to date payment (9th IPC)

Rs. 42,677,056/-
Expected project cost Rs. 67,038,377/-
Present Financial Progress: 64%
Present physical progress 88%


Description
Total Estimated BOQ Quantity
Previous Progress
Present Progress
%age Progress
Excavation works in normal soil
2,101,800 cft
782852 cft
965,782cft
45%
Excavation works in hard rocks
244,000 cft
1,136,593 cft
1,308,201 cft
100% executed Exceed from estimated quantity
Stone works in gabion
388,120  cft
343,490
365,608
94%
PCC works in weir area
16,500
533
533
3.2%
P.C.C (1:1:5:3)
23,770 cft
-
-
-
Steel 9,350 KG - - -
GI wire mesh
382,993
237,489
257,479
67.20%
Stone pitching right bank 25,530 cft - 15,210 59.57%

Construction of Main Gate in Sector D

Contractor: M/s Mian Abdul Jabbar & Co

Up to date payment (3rd IPC)

Rs. 3,450,218/-
Total project cost Rs. 4,384,145 /-
Present Financial Progress 80.75%
Present physical progress 87.50%


Description
Status
%age Progress
Excavation works in Foundation Completed 100%
Foundation work Completed 100%
RCC Column work Completed 100%
Brick work (Guard room) Completed 100%
Slab work (Guard room) Completed 100%
Main gate slab Completed 100%
Fixation of main gate Completed 100%
Finishes work - -