UP-DATE ON DEVELOPMENT WORKS OF THE SOCIETY (UPDATED ON 01-07-2018)

 
Contractor: M/s Mian Abdul Jabbar & Co.
Expected revised project cost Rs. 295,051,303/-

Up to date payment (27th R.B)

Rs. 285,111,446 /-
Date of completion 14-06-2018
Financial Progress 96.63%
Physical progress 99.00%


Items
Description Total Estimated BOQ Quantity Previous Progress
Present
%age Progress
Roads
Embankment (Cft) 33,342 33,342
33,342
100%
Sewerage
Manhole (Nos) 750 742
769
100%
RCC Pipe (Rft) 57,100 51,435
57,982
100%
House Connection (Nos) 350 309
314
89.70%
RCC Pipe (House connection) Rft 13,000 11,575
14,448
100%
Water Supply System
Laying of W/S pipe line (Rft) 61,500 56,656
56,672
92.14%

Drainage System

 

Nullah Excavation (Rft) 4,500 Completed
Completed
100%
Box Culvert
Construction of Culvert (Nos) 2 Completed
Completed
100%
Under Ground Water Reservoir
Construction of Reservoir 2 100
Completed
100%
Parks Development
a) Boundary Wall (Nos) 2 Completed
Completed
100%
b) Grills & Gates (Nos) 2 Completed
Completed
100%
c) Paver Work (No.) 2 Completed
Completed
100%
Additional works (Road widening, Gate, Curb Stones, Guard Rooms etc)
- 100 98
100
100%

Construction of GABION Works (Lake Projects)

Contractor: M/s Sarfaraz Khan Khattak

Up to date payment (13th IPC)

Rs. 68,560,887.83/-
Expected project cost Rs. 76,285,828/-
Financial Progress: 89.87%
Physical progress -
Date of completion 15-07-2018


Description
Total Estimated BOQ Quantity
Previous Progress
Present Progress
%age Progress
Excavation works in normal soil
2,101,800 cft
965,782 cft
973,642
46.32%
Excavation works in hard rocks
244,000 cft
1,308,201 cft
1,559,986
100% executed Exceed from estimated quantity
Stone works in gabion
388,120  cft
643,278
689,472.19
100% executed, exceed from estimated quantity
PCC works in weir area 1:3:6
16,500
533
533
3.2%
Cement concrete work 1:2:4 1,320.00 2,449.00 2,449.00 100% executed, exceed from estimated quantity
RCC works in weir 1:1/2:3
8,500
10,817.76
10,817.76
100% executed, exceed from estimated quantity
Steel 7,590 12,755.31 12,755.31 100%
GI wire mesh 382,993 456,341 497,743 100%
Stone pitching
30,000
33,857
36,694
99%

INSTALLATION OF STREET LIGHT IN SECTOR A & D


Contractor: M/s Margallah Engineering 

Total project cost

Rs. 2,944,810/-
Up to date payment (1stRB) Rs. 2,740,546 /-
Date of completion 01-06-2018
Financial Progress 93.06%
Physical Progress 100%



CONSTRUCTION OF MAIN GATE IN SECTOR D TOWARDS INTERCHANGE


COMMERCIAL PLAZA IN SECTOR C [Completed and ready for possession]


Commercial Plaza in Sector B




GABION WORKS IN SECTOR D [LAKE PROJECT]


Plantation in WAPDA Town Islamabad



Installation of Transformers in Sectors where houses have been constructed