UP-DATE ON DEVELOPMENT WORKS OF THE SOCIETY (UPDATED ON 01-10-2018)


Construction of GABION Works (Lake Projects)

Contractor: M/s Sarfaraz Khan Khattak

Up to date payment (13th RB)

Rs. 68,560,887.83/-
Expected project cost Rs. 76,285,828/-
Financial Progress: 89.87%
Physical progress 95%
Date of completion 15-07-2018


Description
Total Estimated BOQ Quantity
Previous Progress
Present Progress
%age Progress
Excavation works in normal soil
2,101,800 cft
965,782 cft
973,642
46.32%
Excavation works in hard rocks
244,000 cft
1,308,201 cft
1,559,986
100% executed Exceed from estimated quantity
Stone works in gabion
388,120  cft
643,278
689,472.19
100% executed, exceed from estimated quantity
PCC works in weir area 1:3:6
16,500
533
533
3.2%
Cement concrete work 1:2:4 1,320.00 2,449.00 2,449.00 100% executed, exceed from estimated quantity
RCC works in weir 1:1/2:3
8,500
10,817.76
10,817.76
100% executed, exceed from estimated quantity
Steel 7,590 12,755.31 12,755.31 100%
GI wire mesh 382,993 456,341 497,743 100%
Stone pitching
30,000
33,857
36,694
100%

INSTALLATION OF GATE AT WEIR


Contractor: M/s Sarfaraz Khan Khattak

Total project cost

Rs. 2,004,750/-
Up to date payment Rs. 840,000 /-
Date of completion 01-09-2018
Financial Progress 41.90%


Description
Status
%age Progress
Provision of gate at site Completed 100%
Foundation work In progress 30%
Installation of gate Nil Nil

GROUTING OF STONE PITCHING


Contractor: M/s Sarfaraz Khan Khattak

Total project cost

Rs. 1,179,000/-
Up to date payment -
Date of completion 05-09-2018
Financial Progress -


Description
Status
%age Progress
Grouting at site Completed 100%

DEVELOPMENT OF PARK IN SECTOR A


Contractor: M/s Sarfaraz Khan Khattak

Total project cost

Rs. 14,598,695/-
Up to date payment -
Date of completion 05-09-2019
Financial Progress -


Description
Status
%age Progress
Mobilization at site Completed 100%
Survey work Completed 100%

CONSTRUCTION OF MAIN GATE IN SECTOR D TOWARDS INTERCHANGE


COMMERCIAL PLAZA IN SECTOR C [Completed and ready for possession]


Commercial Plaza in Sector B




GABION WORKS IN SECTOR D [LAKE PROJECT]


Plantation in WAPDA Town Islamabad



Installation of Transformers in Sectors where houses have been constructed